Back to project references
Installation ReferenceEnergy Storage

500 kW / 1.2 MWh Containerized BESS

A complete 20-foot BESS supports PV energy storage, time-of-use energy management and grid frequency regulation with a customer-developed EMS.

Czech Republic500 kW / 1.2 MWhPV storage & grid services

Operational · Frequency regulation active

BESS container beside a building with rooftop solar panels in the Czech Republic

Customer site photograph from the installation stage. The project owner confirms the system is now operational.

Select a photograph to open the full-size image.

Project at a glance

Configuration & supply

Container
20-foot integrated BESS
PCS
1 × Sinexcel 500 kW PCS unit
Battery system
6 high-voltage air-cooled lithium battery clusters · 1.2 MWh total
EMS integration
Customer-developed EMS · Modbus point map provided

What FLONCO supplied

  • Complete 20-foot BESS container
  • 6 high-voltage air-cooled lithium battery clusters, totaling 1.2 MWh
  • Sinexcel 500 kW PCS unit
  • Air conditioning and fire protection systems
  • Lighting and monitoring systems
  • Equipment Modbus point map for EMS integration

Public reference note

Operational status and frequency-regulation participation are confirmed by the project owner. Customer photographs document delivery and installation; the final image was taken at the factory before shipment. Original equipment markings are retained.

Customer background & needs

The customer combines PV generation with battery storage and electricity-price-based dispatch. Principal uses are peak shaving and energy shifting: storing PV energy, charging from the grid during low-price periods, and using stored energy on site or exporting during high-price periods. Grid frequency regulation is an additional application.

Our supply scope

FLONCO supplied the complete containerized storage equipment, including batteries, PCS and auxiliaries. The customer developed its own EMS; FLONCO provided the equipment Modbus point map for integration. The rooftop PV equipment in the photos is not included in the stated supply scope.

Project status & application

The project owner confirms that the BESS has been delivered, installed and is operating, with grid frequency regulation already underway. Dispatch is managed through the customer's EMS. No specific trading revenue, savings figures or grid-service certification are claimed.

Site and equipment photographs, with the context of each view.

Delivery: the container arrives on a transport trailer.
Delivery: the container arrives on a transport trailer.
Installation-stage view of the container exterior and prepared site.
Installation-stage view of the container exterior and prepared site.
Installation in progress: battery racks before the modules were fully fitted. Not a current operating-state photograph.
Installation in progress: battery racks before the modules were fully fitted. Not a current operating-state photograph.
Wide site view showing the rooftop PV array and BESS during installation.
Wide site view showing the rooftop PV array and BESS during installation.
Another exterior view from the site installation stage.
Another exterior view from the site installation stage.
Factory photograph before shipment, showing the integrated equipment.
Factory photograph before shipment, showing the integrated equipment.

Planning a similar project?

Let's discuss your system requirements.

Request a Similar Solution